THE INSTALLATION AND START-UP OF THE LIGHTING HAS NOT BEEN EXECUTED

The agreement to legalize the Playa Blanca Partial Plan has also been breached by the promoters

They committed to finishing the urbanization of the area where the houses are located, but they still haven't done so. The City Council has given them a month or will initiate forced execution.

April 4 2019 (01:10 WEST)
The agreement to legalize the Playa Blanca Partial Plan has also been breached by the developers
The agreement to legalize the Playa Blanca Partial Plan has also been breached by the developers

The "Planning and Management Agreement of the Playa Blanca Partial Plan" approved with the new General Plan of Yaiza to cover this illegal plan has also been breached, since the urbanization works that the promoters committed to finish have not been carried out to this day. This is reflected in the decree signed on March 14 by the mayor, Óscar Noda, in which he gives those responsible one month to execute these works.

With the new planning, this Partial Plan -which in reality should not have been developed because it was extinguished since 2001- was divided into two Action Units: UA1, which is the closest to the coast and where the construction of a new hotel was authorized, and UA2, which is where the houses that were illegally built and sold to third parties are located. Under the agreement to legalize this partial plan, the promoters of Action Unit Number 1 "committed to execute the urbanization works that remained to be executed in Action Unit 2, until its complete completion", although to date they have not done so.

Therefore, the mayor has issued a decree declaring the entity Maviera and the Playa Blanca UA1 Owners Community, through its administrator, the entity "Vega Luján", and through its president, Playa Blanca Plots S.L., responsible for this breach. In addition, he gives them a month to execute the pending works. Otherwise, the City Council warns that it will initiate forced execution, directly assuming the works and then charging the amount to these companies.

 

Pending works for more than 77,000 euros


According to the municipal technical report, deficiencies in urban furniture have not been covered in that area and the installation and commissioning of public lighting has not been carried out, with the value of these works being estimated at 77,614 euros. In the event that the City Council assumed the works, it warns that it would recover part of that money through the guarantee deposited in its day as a bond. However, the amount of that guarantee is 48,673.70 euros, so it would not cover the total amount. Thus, in the event that the City Council took charge of executing the works, it would then have to claim the difference from those responsible.

In addition, the decree also indicates that interventions in the sewage system and in the EBAR are still pending, although they are not included in this file since they also affect the other Action Unit, Number 1. In this regard, the resolution indicates that the sewage system "cannot be dismembered by sections, making it impossible to receive it in parts", so this breach will be processed in another procedure. 

Most read