The state commercial company Aguas de las Cuencas de España (ACUAES) has sent the tender for the works of the Yaiza and Uga collectors to the Official Journal of the European Union (OJEU), budgeted at 6,066,313 euros, along with another 304,935 euros allocated to technical assistance and project management.
The intervention will allow for the collection of wastewater from both settlements to pump it to the Puerto Calero pumping station and treat it at the wastewater treatment plant in Tías, where it will be regenerated for reuse.
This contract comes after the president of ACUAES, María Rosa Cobo, and the president of the Cabildo and the Lanzarote Water Consortium, Oswaldo Betancort, digitally signed a second addendum to the collaboration agreement yesterday.
The new agreement increases the investment ceiling in sanitation and wastewater treatment infrastructure on the island from the initial 37.5 million to 52.5 million euros, with the aim of resolving non-compliance with European directives regarding discharges and wastewater treatment.
Details of the new network and expansions in Tías, Arrecife, and Puerto Calero
The tendered project includes the installation of 11.2 kilometers of wastewater collectors and 6.2 kilometers of regenerated water pipeline to supply the primary sector. Additionally, three pumping stations (EBAR) will be built in Yaiza, Uga, and Barranco del Agua, as well as a regenerated water tank that will supply both agricultural irrigation and municipal cleaning and garden watering services.
The plan also includes a new terrestrial outfall in Tías and the rehabilitation of the diffusers of the current submarine outfall to improve discharge dilution, although these two actions remain pending tender until the reservation of the Maritime-Terrestrial Public Domain is completed.
In parallel, ACUAES has updated the status of the two large wastewater treatment plants under construction on the island. In the case of the Arrecife wastewater treatment plant, the expansion—sized for 126,000 equivalent inhabitants—is at 88% completion. With the civil works already finished, the work now focuses on electromechanical equipment and the perimeter enclosure, maintaining the forecast of completion in July 2027. On the other hand, on October 7, the drafting of the project to complete the capital's outfall was awarded for 53,359 euros to the company Ingiopsa Ingeniería, with a deadline of five months.
For its part, in the Tías and Puerto Calero treatment plant, after the site survey report was signed on August 10, the works have begun with earthmoving for the new secondary settling tank and the channeling of the ravine, in addition to the actions in Puerto Calero. The works in Puerto Calero will conclude in January 2028, while the expansion of the Tías treatment plant will finish in May 2028, followed by a six-month commissioning period.
The set of these investments will be co-financed 50% by the European FEDER funds (2021-2027) allocated to the Ministry for the Ecological Transition and the Demographic Challenge. The remaining half will be advanced by ACUAES —40% with its own funds and 10% through a loan— and later recovered from the Water Consortium through tariffs once the new facilities come into service.