This is how the more than 4 million from water will be distributed in Lanzarote: networks, ravines, and irrigation

The Insular Council of Waters of Lanzarote will allocate 2.94 million euros in 2027 to renew networks and clean ravines, including actions in La Graciosa and the irrigation of Tinajo.

CONSEJO INSULAR DE AGUAS  (5)
CONSEJO INSULAR DE AGUAS (5)

The Insular Water Council of Lanzarote (CIAL) has approved in an ordinary session of its General Board, the budget project for the year 2027. The amount amounts to 4,169,800 euros, which represents an increase of 1.3 million euros (45.3% more) compared to the year 2026.

The accounts, balanced in income and expenses, allocate 2,944,468 euros to the investment chapter, a figure that is equivalent to 70.6% of the total budgeted. According to the president of the Cabildo and the organization, Oswaldo Betancort, this item is aimed at improving hydraulic infrastructures, reducing network losses, and preventing floods.

Within the investment breakdown for 2027, the largest item corresponds to the renovation of supply networks in Lanzarote and La Graciosa, endowed with 1.5 million euros, followed by the 500,000 euros allocated to cleaning and conditioning of ravines. Both lines of action have financing from the Cabildo and will be executed through two framework agreements that, as indicated by the Minister of Water and Vice President of the CIAL, Domingo Cejas, will allow the mobilization of up to five million euros in multi-year contracting with the Water Consortium.

Likewise, the budget includes 552,448 euros for the first phase of the irrigation management building in the northeast, located in Tinajo, to which are added 299,540 euros for complementary works in these same facilities. The investment chapter is completed with 55,480 euros for a pilot measurement system at the discharge point of the Costa Teguise treatment plant and 16,000 euros for the expropriation of land intended for the installation of hydrants.

Finally, the General Board ratified the Vice Presidency's resolution to initiate the joint environmental processing before the competent body of the Government of the Canary Islands of the fourth cycle of the Insular Hydrological Plan and the third cycle of the Flood Risk Management Plan, both planned for the period 2027-2033.