The planning of the electric transport network with a 2030 horizon approved this Friday by the Council of Ministers foresees for the Canary Islands 26 new substations and 452 kilometers of new power lines, to reinforce the security of supply, anticipate the challenges of electrification, integrate more renewables and respond to new demands for electricity from renewables.
The plan, which is binding for Red Eléctrica, also includes actions on existing facilities and the repowering of another 26 kilometers of lines to increase their capacity, as the company reported in a statement.
Among the actions considered preferential for the archipelago are the installation of reactors and synchronous compensators to reinforce the stability of the island electrical systems, as well as new 220 kilovolt axes in Gran Canaria and Tenerife, the conversion to double circuit of the West ring of Tenerife and the Tías-Playa Blanca axis in Lanzarote.
The planning also incorporates actions in Lanzarote and Fuerteventura, including the double circuit Playa Blanca-Tías of 132 kilovolts, the renovation of the submarine link between Lanzarote and La Graciosa and new substations in Haría, Arrecife and Cañada de la Barca.
In La Palma, the planning foresees new substations in Las Breñas, Fuencaliente and Tajuya, which will increase the security and quality of supply, as well as progress in the island's energy transition.
The document also incorporates a synchronous compensator in Fuencaliente to increase the robustness of the system.
In Tenerife, the plan contemplates a new north-south 220 kilovolt axis between Granadilla and Candelaria, with a connection at the future Las Rosas substation, as well as the closure in double circuit of the west ring through the Los Olivos-Chío-Drago axis.
Likewise, new infrastructures are foreseen to meet the growth in electricity demand associated with the ports of the capital and Granadilla and the industrial and residential development of the northern metropolitan area of Tenerife, such as the substations of Lomo Pelado, Tíncer and Las Américas and the expansion of the Abona substation.
In addition to reinforcing the north-south axis, in Gran Canaria, the main actions include the new substation of Puerto de La Luz, intended to cover the needs arising from port electrification and the electrical supply to ships, and new infrastructures in Las Palmas Oeste, La Paterna and Mogán.
The document includes, beyond 2030, the future submarine link between Gran Canaria and Fuerteventura to reinforce the integration of both island electrical systems, as well as the future Zurita substation, in Fuerteventura, as a development to consider for reinforcing the island's transport network.
The state planning of the electrical transport network foresees a total investment of 17,143 million euros throughout Spain and includes the construction of 193 substation parks and 6,707 kilometers of new electrical lines throughout the national territory.